ESD compliance verification per IEC 61340-5-1: why regular testing matters
An EPA only protects as long as wrist straps, worksurfaces, floors and ionisers actually work. That is why IEC 61340-5-1 requires regular compliance verification according to a fixed plan. We show what is tested, why it matters and which Desco test equipment is available for the job.
View the ESD survey kitContents
Why regular compliance verification matters
ESD control items wear out, get dirty or lose their ground connection, and you usually cannot see it. Only a measurement shows whether the protection still works in daily operation.
A coiled cord can look undamaged on the outside and still be broken inside. A bench mat loses its dissipative properties through wear, dirt or cleaning agents, and an ioniser drifts out of balance over time. If a single item fails, the ESD sensitive devices at that workstation are no longer protected, often without anyone noticing.
Compliance verification is therefore a requirement of IEC 61340-5-1. It ensures that ESD control measures keep working on an ongoing basis, and the test records provide evidence for audits and customers.
What a verification plan must define
According to IEC 61340-5-1, measurements are carried out according to a written compliance verification plan. It is part of the ESD control programme.
- Items: which technical requirements and ESD control items are verified
- Limits: which measured values count as a pass
- Intervals: how often each item is tested
- Test methods: which procedure is used, the methods are described in IEC TS 61340-5-4
- Records: test records as evidence of conformity
- Test equipment: instruments capable of making the measurements defined in the plan
Each organisation sets its own intervals. They depend on how heavily an item is used, how quickly it wears and how sensitive the devices are. As typical practice, Desco mentions testing wrist straps before each shift and worksurfaces at least quarterly.
What is tested in the EPA
Every ESD control item included in the ESD control programme is tested, from grounding to ionisation.
| Item | Typical measurement |
|---|---|
| Grounding | Ground points and protective earth, impedance and noise voltage |
| Worksurfaces and shelving | Resistance to ground (Rg) and point to point (Rp-p), for worksurfaces the standard requires Rg below 1 x 109 ohms |
| Floors | Floor resistance and person, footwear and floor as a system |
| Personnel grounding | Wrist strap and ESD footwear, tested while worn |
| Seating and mobile equipment | Resistance to ground of chairs and carts |
| Garments, gloves, packaging | Resistance measurement on ESD garments, gloves, finger cots and packaging |
| Ionisers | Offset voltage (balance) and discharge times in both polarities |
| Continuous monitoring | Checking the limits of workstation monitors |

Many companies test personnel grounding daily at the EPA entrance, for example with the Combo Tester X3 19270, which tests the wrist strap and both shoes in one go. More on personnel grounding in our guide Wrist strap and heel strap.
Desco test equipment for verification
For regular measurements in the EPA we stock Desco test equipment, from the complete survey kit to the handy surface resistance checker.

The Desco ESD survey kit 222698 combines the instruments for the most important routine tests per IEC 61340-5-1: resistance measurement on worksurfaces, shelving, carts, floors, garments and seating, a hand electrode for person and footwear, an AC outlet and wrist strap tester, a low resistance tester for ground sockets and an ionisation test kit.

Digital meter with electrodes, point to point and to ground, 10 V and 100 V, internal memory.
View productAnalogue display with 2.27 kg electrodes and automatic test voltage selection.
View productQuick spot checks on mats, packaging and containers with built-in electrodes.
View productMeasures body voltage per EN 61340-4-5 to assess footwear and flooring.
View productTests wrist strap and both shoes at the EPA entrance, with relay output for access control.
View productMore test and measuring equipment for ESD protected areas in the shop.
View categoryTesting ionisers and grounding
Ionisers and ground points work quietly in the background. That is exactly why they belong in the verification plan with fixed intervals.

The new Desco ioniser verification kit 19433, together with the static field meter 19432, measures the offset voltage and discharge times of an ioniser right at the workstation, per ANSI/ESD SP3.3 and ESD TR53. The ioniser does not need to be removed.

For the grounding itself, the SCS Ground Pro Meter CTM051 is a good fit. It measures the impedance of a ground point and also shows voltage and EMI on the protective earth, typical causes of EOS damage, for example on soldering irons.
Testers and monitors need checking too
A measurement is only as reliable as the instrument that makes it. Testers and continuous monitors therefore also belong in the verification plan.
Desco recommends annual calibration of testers and monitors. In between, the limits can be checked on site without removing the units:
- EMIT limit comparator 50424 for Combo Tester X3 and SmartLog Pro 2
- Verification tester 770065 for the 724 Workstation Monitor and the 725 wrist strap monitor
- Verification tester 98221 for Desco Wave Distortion monitors
Training and webinars from Desco Europe
Test equipment alone is not enough, the people testing also need to master the procedures. Desco Europe supports this with training courses and technical webinars.
The Compliance Verification Training Courses from Desco Europe focus on the equipment needed to validate an ESD programme to IEC 61340-5-1 and on carrying out the tests according to the methods of IEC TS 61340-5-4. They are aimed at everyone who carries out regular verification testing, such as ESD coordinators, production supervisors and quality engineers.
In addition there is the Technical Webinar series. The next live webinar on grounding and personnel grounding takes place on 20 November 2026 at 10:00 GMT and lasts about 40 minutes including Q&A. Topics are proper grounding, the differences between equipment and personnel grounding, implementation and testing in practice, and common mistakes.
Frequently asked questions
Is compliance verification per IEC 61340-5-1 mandatory?
Yes. Anyone running an ESD control programme per IEC 61340-5-1 must establish a compliance verification plan, measure according to it and document the results.
How often do I need to test?
The standard leaves the intervals to the user, they are defined in the verification plan. As typical practice, Desco mentions testing wrist straps before each shift and worksurfaces at least quarterly.
Which test methods apply to verification?
The test methods for compliance verification are described in IEC TS 61340-5-4. If other methods are used, the organisation must be able to show that they are equivalent.
Which meter do I need to get started?
For worksurfaces, shelving and floors, a surface resistance meter with electrodes such as the Desco 19290 kit is sufficient. To cover all routine tests, the ESD survey kit 222698 combines the right instruments in one case.
Do the testers themselves need to be checked?
Yes. Desco recommends annual calibration of testers and monitors. In between, the limits can be checked on site with verification testers.
Enquire about Desco test equipment
Setting up your verification plan or adding to your test equipment? Tell us what you want to test and we will send you a quote.
Desco in our range
Quote and delivery from a single source.
Calibrated equipment
Desco testers with NIST traceable calibration.
Standard in focus
Test equipment for testing per IEC 61340-5-1.
Selection help
We help you choose the right products; technical details are clarified with the manufacturer.